Env: ALL

Executive Status

EnvEnvironment partition: dev, int, stg, or prod.
GoalConfigured success target and run scope for this environment. INT/STG/PROD use all E2E job runs. DEV uses post-good runs plus Tide batches: runs on the final commit of a PR that later merged, or batch retests of PRs that passed their individual e2e-parallel checks.
RunsNumber of job runs in the selected goal definition for this environment.
SuccessSuccess rate on the selected goal definition: (runs - failed runs) / runs * 100.
Gap vs targetDifference in percentage points between current success and the configured target rate.
Change vs prevHow much the success rate changed compared with the immediately preceding equal-length window, using the same goal definition as this row.
Provision successProvisioning here means infrastructure setup before E2E tests start. A run counts as provision-successful if it got past provisioning, even if it later failed during E2E. Runs that failed for 'Other' CI-infrastructure reasons are excluded because those runs never reached the provision step. DEV rows use post-good runs plus Tide batches. INT/STG/PROD show n/a because provisioning is not part of those environments.
Provision change vs prevChange in provision success, in percentage points, compared with the previous equal-length window. Uses the same provision-success definition as the Provision success column. DEV only; INT/STG/PROD show n/a.
E2E successAmong runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step. DEV rows use only runs after the final push to a PR that later merged. INT/STG/PROD use all E2E job runs.
E2E success vs prevChange in E2E success, in percentage points, compared with the previous equal-length window. Uses the same E2E-success definition as the E2E success column.
DEV95% - Post-good runs + Tide batches19422.16% (off track)-72.84ppn/a100.00% (43/43)n/a100.00% (43/43)n/a
INT95% - All E2E job runs1776.47% (off track)-18.53ppn/an/an/a100.00% (13/13)n/a
STG95% - All E2E job runs1612.50% (off track)-82.50ppn/an/an/a100.00% (2/2)n/a
PROD95% - All E2E job runs130.00% (off track)-95.00ppn/an/an/an/an/a

Environment: DEV

E2E Jobs
451
Success Rate
16.19%
Provision success
Provisioning here means infrastructure setup before E2E tests start. A run counts as provision-successful if it got past provisioning, even if it later failed during E2E. Runs that failed for 'Other' CI-infrastructure reasons are excluded because those runs never reached the provision step.
100.00% (73/73)
E2E success
Among runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step.
100.00% (73/73)
E2E Jobs (post-good + batches)
These PR-regression-filtered DEV metrics include runs on the final commit of a PR that later merged, plus Tide batch retests of PRs that passed their individual e2e-parallel checks. Each run counts once. This card shows the number of runs in that DEV-only goal basis.
194
Success Rate (post-good + batches)
These PR-regression-filtered DEV metrics include runs on the final commit of a PR that later merged, plus Tide batch retests of PRs that passed their individual e2e-parallel checks. Each run counts once. This card shows the overall success rate for that DEV-only goal basis.
22.16%
Provision success (post-good + batches)
These PR-regression-filtered DEV metrics include runs on the final commit of a PR that later merged, plus Tide batch retests of PRs that passed their individual e2e-parallel checks. Each run counts once. Provisioning here means infrastructure setup before E2E tests start. A run counts as provision-successful if it got past provisioning, even if it later failed during E2E. Runs that failed for 'Other' CI-infrastructure reasons are excluded because those runs never reached the provision step.
100.00% (43/43)
E2E success (post-good + batches)
These PR-regression-filtered DEV metrics include runs on the final commit of a PR that later merged, plus Tide batch retests of PRs that passed their individual e2e-parallel checks. Each run counts once. Among runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step.
100.00% (43/43)

Daily Run Outcomes

Successful runs Provision failures E2E failures Other failures
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
86 runs
20%Successful runs: 17 of 86 runs (19.8%)
80%Other failures: 69 of 86 runs (80.2%)
155 runs
12%Successful runs: 19 of 155 runs (12.3%)
88%Other failures: 136 of 155 runs (87.7%)
146 runs
15%Successful runs: 22 of 146 runs (15.1%)
85%Other failures: 124 of 146 runs (84.9%)
28 runs
Successful runs: 7 of 28 runs (25.0%)
75%Other failures: 21 of 28 runs (75.0%)
36 runs
Successful runs: 8 of 36 runs (22.2%)
78%Other failures: 28 of 36 runs (77.8%)

Daily Run Outcomes for DEV Goal Basis (post-good + batches)

Successful runs (post-good + batches) Provision failures E2E failures Other failures
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
32 runs
31%Successful runs (post-good + batches): 10 of 32 runs (31.2%)
69%Other failures: 22 of 32 runs (68.8%)
71 runs
14%Successful runs (post-good + batches): 10 of 71 runs (14.1%)
86%Other failures: 61 of 71 runs (85.9%)
55 runs
25%Successful runs (post-good + batches): 14 of 55 runs (25.5%)
75%Other failures: 41 of 55 runs (74.5%)
17 runs
Successful runs (post-good + batches): 4 of 17 runs (23.5%)
76%Other failures: 13 of 17 runs (76.5%)
19 runs
Successful runs (post-good + batches): 5 of 19 runs (26.3%)
74%Other failures: 14 of 19 runs (73.7%)

Environment: INT

E2E Jobs
17
Success Rate
76.47%
E2E success
Among runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step.
100.00% (13/13)

Daily Run Outcomes

Successful runs Provision failures E2E failures Other failures
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
2 runs
100%Successful runs: 2 of 2 runs (100.0%)
7 runs
57%Successful runs: 4 of 7 runs (57.1%)
43%Other failures: 3 of 7 runs (42.9%)
3 runs
67%Successful runs: 2 of 3 runs (66.7%)
33%Other failures: 1 of 3 runs (33.3%)
3 runs
100%Successful runs: 3 of 3 runs (100.0%)
2 runs
100%Successful runs: 2 of 2 runs (100.0%)

Environment: STG

E2E Jobs
16
Success Rate
12.50%
E2E success
Among runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step.
100.00% (2/2)

Daily Run Outcomes

Successful runs Provision failures E2E failures Other failures
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
2 runs
50%Successful runs: 1 of 2 runs (50.0%)
50%Other failures: 1 of 2 runs (50.0%)
5 runs
100%Other failures: 5 of 5 runs (100.0%)
5 runs
20%Successful runs: 1 of 5 runs (20.0%)
80%Other failures: 4 of 5 runs (80.0%)
2 runs
100%Other failures: 2 of 2 runs (100.0%)
2 runs
100%Other failures: 2 of 2 runs (100.0%)

Environment: PROD

E2E Jobs
13
Success Rate
0.00%
E2E success
Among runs that reached E2E execution, this shows how many completed successfully. Provision failures and 'Other' CI-infrastructure failures are excluded because those runs never reached the E2E step.
n/a

Daily Run Outcomes

Successful runs Provision failures E2E failures Other failures
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
0 runs
No runs
2 runs
100%Other failures: 2 of 2 runs (100.0%)
5 runs
100%Other failures: 5 of 5 runs (100.0%)
2 runs
100%Other failures: 2 of 2 runs (100.0%)
2 runs
100%Other failures: 2 of 2 runs (100.0%)
2 runs
100%Other failures: 2 of 2 runs (100.0%)